Hi Paul,
for these things to check, we need to have information on the masterdata set up:
workcenter:
- standard value keys and formulae (for capacity and scheduling).
- finite capacity scheduling has been chosen or not?
- available capacity and utilization details.
Routing:
- what are the quantities and times defined for the operations.
- whether lead time scheduling has been chosen during MRP run?
what are the results shown by MRP run? and you might want to look into capacity evaluation and leveling transaction also.
Regards,
Sandeep